Case Study 1: Anglia CP6 Wheel Timber Bridge Renewals, Year 3
TECS supported Taziker in the delivery of the survey, design, and installation of 5no Wheel Timber Bridge (WTB) renewals.
TECS supported Taziker in the delivery of the survey, design, and installation of 5no Wheel Timber Bridge (WTB) renewals. Sites included Bretts Hill, North Walsham, Occupational Drove, Cantley Lane, and River Tas (and flood spans). The works were of an urgent nature due to the ongoing deterioration of the assets. This resulted in tight time constraints to complete the required surveys and designs. Successful delivery of the project required all stakeholders to undertake a collaborative approach to ensure the programme could be achieved; due to the limited access and tight timescales.
Site Survey
Civil/structural site visit and inspection notes
3D CAD surveying
Structure gauging
Site photographs and survey sheets
P-Way
Design Report including:
Commentary
Form A/B Track (Certificates)
Design Risk Assessment
IDC Certificate
Schedule of Works (Specification Page)
Track Design
Track Alignment
Gauging Assessment
ESR & TSR Design
General Arrangement Drawing including:
Horizontal track alignment and Vertical profile
Horizontal layout and vertical profile of proposed drainage
Track cross sections
Civil Engineering
Form F001/F002/F003 Certificates
Preliminary and detailed calculations as necessary
Drawings
Specification Document (Proposed as notes on the drawing)
Project Delivery
Engineering and Management Support
Project Planning support
Supply of Site staff
Delivery of works and handover support
The five designs were delivered over five weeks with surveys feeding into this and overlapping with the design works. This was due to the planned access constrained to three delivery weekends across the five bridges. TECS utilised two design houses to support the P-way and Civil Engineering design; which we managed. Programme captured below.
The project was a success and all designs were delivered on time which allowed all the planned weekends to progress as planned.
Power in Numbers
30
Staff
50
Duration
200
Other