top of page

Case Study 1: Anglia CP6 Wheel Timber Bridge Renewals, Year 3

TECS supported Taziker in the delivery of the survey, design, and installation of 5no Wheel Timber Bridge (WTB) renewals.

TECS supported Taziker in the delivery of the survey, design, and installation of 5no Wheel Timber Bridge (WTB) renewals. Sites included Bretts Hill, North Walsham, Occupational Drove, Cantley Lane, and River Tas (and flood spans). The works were of an urgent nature due to the ongoing deterioration of the assets. This resulted in tight time constraints to complete the required surveys and designs. Successful delivery of the project required all stakeholders to undertake a collaborative approach to ensure the programme could be achieved; due to the limited access and tight timescales.





  1. Site Survey

    • Civil/structural site visit and inspection notes

    • 3D CAD surveying

    • Structure gauging

    • Site photographs and survey sheets


  1. P-Way

Design Report including:

  • Commentary

  • Form A/B Track (Certificates)

  • Design Risk Assessment

  • IDC Certificate

  • Schedule of Works (Specification Page)


Track Design

  • Track Alignment

  • Gauging Assessment

  • ESR & TSR Design


General Arrangement Drawing including:

  • Horizontal track alignment and Vertical profile

  • Horizontal layout and vertical profile of proposed drainage

  • Track cross sections


  1. Civil Engineering

    • Form F001/F002/F003 Certificates

    • Preliminary and detailed calculations as necessary

    • Drawings

    • Specification Document (Proposed as notes on the drawing)


  1. Project Delivery

    • Engineering and Management Support

    • Project Planning support

    • Supply of Site staff

    • Delivery of works and handover support


The five designs were delivered over five weeks with surveys feeding into this and overlapping with the design works. This was due to the planned access constrained to three delivery weekends across the five bridges. TECS utilised two design houses to support the P-way and Civil Engineering design; which we managed. Programme captured below.





The project was a success and all designs were delivered on time which allowed all the planned weekends to progress as planned.




Power in Numbers

30

Staff

50

Duration

200

Other

Project Gallery

Download Case Study

download-icon-download+file+files+pdf+icon-1320184619509952330_512.png
bottom of page